The percentages at the bottom of each stage refer to the accuracy of
quantitative data that can be achieved for that stage. Some of you may not like
the figures but that can form the basis of a different argument in a later
article.
3. The origin risk
In the proposal stage the idea for the project is barely formed and the
accuracy of quantitative data is only 50%. Agreed, some basic design is required
to formulate a proposal but this is done only in conceptual terms.
Failure to understand this aspect leads to the full design being done in the
proposal stage, thereby incurring huge costs before the project is fully
approved. My experience has shown that if the accuracy of quantitative data is
understood and explained to the client and the sponsor at this juncture, a
better understanding of cost escalation and the management of resource
constraints is obtained.
During the proposal stage the feasibility study is undertaken. It is during
this study that factors concerned with market opportunity, environment,
government legislation and pressure groups are investigated.
These issues are what I call "Project Killers". These are risks
that impact directly on project viability. That is if they occur they stop the
project totally.
All to often these days stakeholders are not consulted during feasibility and
only get to hear about it in the implementation stage. This results in a huge
uproar and clashes between stakeholders and the project team leading to delays
and escalated costs.
If managed correctly project risk is identified, quantified, the response
developed and controlled in the proposal stage.
Although the product is described in the proposal stage and referred to
during feasibility full design has to be done in order for the risk to be
quantified adequately. This occurs in the planning stage.
If the project has not been approved to proceed with resource expenditure,
how can product risk exist? Product risk originates in the design of the product
that the project is to produce, which is in the planning stage.
4. The impact of risk
Risk cannot impact before it originates. Therefore product risk cannot have
an impact on the proposal stage. Only project risk impacts on the proposal
stage.
Product risk impact on the planning stage is a moot point. It is possible but
not probable. The risk is more likely to impact on some future time period.
Based on practical experience I have found product risk to impact only in the
construction stage as design flaws, weather conditions and supplier foul ups
occur most frequently during construction.
Product risk originates in design then it impacts in implementation. Project
risk on the other hand if not dealt with adequitly in the proposal stage will
continue to plague the project and has the potential to "kill" the
project in any stage.
Once the proposal and planning stages are completed no amount of
modifications during the construction stage will repair a basically poor design.
If product risk originates in the design then it must be eliminated during
the planning stage.
If project risk originates in the feasibility then it must be eliminated
during the proposal stage.
5. Managing risk
I was requested by a colleague who was working on a classified project to
develop a new kind of alarm system for which the technology to develop it did
not exist; i.e. a high risk project.
Here’s how we solved it
During design a number of insurmountable product risks were identified, the
impact of each could cancel the project.
What I proposed was that when such a risk was identified it should be made
the end condition of a stage in the life cycle. The project would not progress
until the risk was eliminated. The entire project team would focus on the
identified risk until it was solved.
The project has proceeded with success achieving an international patient as
"Alarm State Navigation".
Let me show you what I mean with an example project life cycle.